Here's today's 2q12 results NR that includes the latest hike call, here's the chunk of script:
Pascua-Lama Cost Increase- Due to lower than expected productivity and persistent inflationary and other cost pressures, as previously disclosed, the company initiated a detailed review of the cost and schedule estimates for Pascua-Lama in the second quarter. Preliminary results currently indicate an approximate 50-60 percent increase in capital costs from the top end of the previously announced estimate of $4.7-$5.0 billion, with first production expected in mid-2014. The company will provide a further progress update with third quarter results.